it is o.k.   time starts from the day on which the rti appliction is recieved in pio office.
     moreover, in exeptional cases; the pio may take 45 days also; giving the reason of delay.
 moreover, 2- 3 days delay is no delay as per govt machinery arguements.
so it is o.k.
vijendra singh, meerut

On Wed, Feb 15, 2012 at 9:35 PM, sarbajit roy <sroy.mb@gmail.com> wrote:
Answer to your query

1) As per general clause act, while counting days the day of the
application will not be counted.
2) The 30 days will start from the time the PIO "receives"  the
request, not from when you filed it.

Jan has 31 days.

Sarbajit

On Feb 15, 8:11 pm, Kumar Gaurav <simple.gau...@yahoo.com> wrote:
> Hello Sir,
>
> This is Gaurav from haridwar.
>
> Sir, I need your help in a very simple issue.
>
> Consider the following case -
>
> RTI application file on date 5.1.2012
>
> PIO responded on 5.2.2012,
>
> Is this a voilation of RTI time frame of 30 days. or this is OK.
>
> Thanks.
>
> Gaurav Sharma
> 9837779669



--
Vijendra Singh